01

EXCAVATION

The site is set out and excavated to the agreed size and depth, with access, soil and drainage checked before work moves on.

02

FORMWORK

Formwork is set up to shape the base and any surrounding slabs, accurately levelled to the approved design.

03

STEELFIXING

Reinforcing steel is placed and tied to engineering requirements to give the concrete its strength.

04

CONCRETING

The concrete base is poured and finished. For modular pools, the fibreglass wall panels are bolted together and fixed to the base.

05

LANDSCAPING

Backfilling and landscaping bring the ground back up around the pool and tie the project into the surrounding site.

06

FENCING

Compliant pool fencing and gates are installed to meet Australian safety requirements.

07

FINISH AND SURROUNDS

The interior liner or tiles go in, followed by coping and surrounds in your chosen tile, sandstone or granite. Equipment is connected and tested.

08

HANDOVER

We fill, commission and test the system, show you how everything works and hand over. Our support continues after handover.